1. need to keep the concrete stiff or it will slide if to wet. dont add water, just use it as its delivered.
2.after screeding and floating allow it to dry slightly, because its on a slope the bleed water will slowly run.brush across the shortest distance with a soft floor brush. if it looks a mess its to wet, brush off water and wait 10-20mins, then repeat. this provides a non slip surface.after brushing pull a trowel down the outside edge keeping it tight to the shutter/form. a 4inch trowel would be recomended as a nice border width.
3.i suppose a 40newton or less even with a 20%slump will be ok, ask when your ordering it, the supplyer will advise you. but a 4;2;1 with 10 mm or less is ideal.
4.no need for plastic, it acts as a damp proofer,not really needed in the path,unless 1: your joining the path to your house or its touching a building where damp will damage the property. 2: there is a lot of weeds, likely to grow up through the path. if your worried about it drying too quick, dampen the hardcore with a hose before starting.
yes also put plastic over the top to stop the sun curing it too fast,try to have it 50mm above the path to let it breathe and spray it every couple of hours with a hose on light spray or a watering can. the longer it is curing/drying the harder it becomes.
also it is a good idea to lightly paint the forms with diesel before you start as they will come away alot easier.leave them for 2-3 days before you remove them,to ensure no damage occours to the edges of the path. add an expansion joint about every 8 feet. it is just a line cut with a pointing trowel a third the depth of the path. or you can buy special grovers to do this but this way is fine.
hope this helps you,
any more questions, just contact me.